Florida Gas Transmission Mainline Hydrostatic Test






Click Here for the
24-Inch Pipeline (North) Project

(along SR 826 from W 68th Street to just before the Golden Glades Interchange)

Test Completed
October 30, 2015







Click Here for the
North Project

(From the Golden Glades Interchange to the interchange of NW 122nd Street )

Test Completed
April 19, 2017





Click Here for the Central Project
(along, and to the north and south of,
NW 74th Street)

Test Completed
March 25, 2019







Click Here for the
South Project

(along Milam Dairy Road, West Flagler Street and Galloway Road)

Test Completed
November 18, 2017